Water supply in Salamis
The approved feasibility study includes:
• The complete construction of an onshore pipeline in Attica along the old Athens – Corinth National Road. The length of the onshore section totals 4,900.00m (3,480.00m Φ1000, 1,390.00m Φ800, 25.00m Φ500 in two branches constituting the starting-point of the twin undersea HDPE Φ560 pipeline).
• The complete construction of a twin undersea HDPE Φ560 pipeline connecting Attica – Salamis in the Nea Perama – Faneromeni sound at a maximum depth of 9.00m. The length of the pipe is 825.00m.
• The complete construction of an onshore Φ800 steel pipeline on the island of Salamis with a length of 7,300.00m.
Project OwnerTHE WATER SUPPLY & SEWERAGE COMPANY (EYDAP)
Group CompanyKL. G. ROUTSIS SA
-